[Issue #251] Batch A plan hardening: execution checks + rollback + parallelization #262

Merged
integrator-bot merged 1 commits from dev/issue-251-batch-a-shell-router into main 2026-03-02 03:51:45 +01:00
Owner

Closes #251

Summary

This micro-PR hardens the release-often lane plan so it is directly executable by DEV runners and reviewers.

What changed

  • Converted issue acceptance checklist to completed, auditable items.
  • Added explicit per-batch done criteria, merge checks, and rollback notes.
  • Added a dependency/parallelization section clarifying what can run in parallel without merge conflict risk.
  • Tightened batch naming to A/B/C alignment from issue text (shell/router, session+i18n wiring, lobby/join/start minimal flow).
  • Added concrete code-area pointers and command-level test expectations per batch.

Why this is useful now

  • Reduces risk of oversized PRs and sequencing ambiguity in SPA MVP lane.
  • Gives operations a clear rollback posture before runtime changes land.
  • Makes follow-up micro-PRs merge/release-ready with less coordination overhead.

Out of scope

  • No runtime code changes in this PR.
  • No quality gate changes.

Evidence

  • Auth preflight and push-path verification performed before edits.
  • Branch is issue-bound and rebased from origin/main.
Closes #251 ## Summary This micro-PR hardens the release-often lane plan so it is directly executable by DEV runners and reviewers. ### What changed - Converted issue acceptance checklist to completed, auditable items. - Added explicit per-batch done criteria, merge checks, and rollback notes. - Added a dependency/parallelization section clarifying what can run in parallel without merge conflict risk. - Tightened batch naming to A/B/C alignment from issue text (shell/router, session+i18n wiring, lobby/join/start minimal flow). - Added concrete code-area pointers and command-level test expectations per batch. ## Why this is useful now - Reduces risk of oversized PRs and sequencing ambiguity in SPA MVP lane. - Gives operations a clear rollback posture before runtime changes land. - Makes follow-up micro-PRs merge/release-ready with less coordination overhead. ## Out of scope - No runtime code changes in this PR. - No quality gate changes. ## Evidence - Auth preflight and push-path verification performed before edits. - Branch is issue-bound and rebased from `origin/main`.
dev-bot added 1 commit 2026-03-02 03:45:43 +01:00
docs(issue-251): make 3-batch SPA lane execution-ready
All checks were successful
CI / test-and-quality (push) Successful in 3m33s
CI / test-and-quality (pull_request) Successful in 3m36s
f9e1999e74
reviewer-bot approved these changes 2026-03-02 03:47:32 +01:00
reviewer-bot left a comment
Owner

God gennemgang af plan-hærdningen for issue #251.

Checks udført:

  • Verificeret at planen nu er præcist 3 batches (A->B->C) med tydelig dependency-rækkefølge.
  • Verificeret per-batch: leverancer (kodeområder), done-kriterier, checks før merge og rollback-note.
  • Verificeret scope-kontrol ("Ikke med i batch") og konkret lane-opgavebinding til PR-navne.
  • Ændringen er dokumentations-only (ingen runtime-kode ændret i denne PR).

Ingen blockers fundet fra review-siden.

God gennemgang af plan-hærdningen for issue #251. Checks udført: - Verificeret at planen nu er præcist 3 batches (A->B->C) med tydelig dependency-rækkefølge. - Verificeret per-batch: leverancer (kodeområder), done-kriterier, checks før merge og rollback-note. - Verificeret scope-kontrol ("Ikke med i batch") og konkret lane-opgavebinding til PR-navne. - Ændringen er dokumentations-only (ingen runtime-kode ændret i denne PR). Ingen blockers fundet fra review-siden.

SEVERITY: HIGH (merge gate)

Blocker for merge:

  • Required CI checks are not green for head f9e1999e74cebad9a4e5c928813ea10b59d61b7a.
  • Current combined status is pending with 2 pending contexts:
    • CI / test-and-quality (push)
    • CI / test-and-quality (pull_request)

I will not merge until all required checks are green.

SEVERITY: HIGH (merge gate) Blocker for merge: - Required CI checks are not green for head `f9e1999e74cebad9a4e5c928813ea10b59d61b7a`. - Current combined status is `pending` with 2 pending contexts: - `CI / test-and-quality (push)` - `CI / test-and-quality (pull_request)` I will not merge until all required checks are green.
integrator-bot merged commit 377fb712e1 into main 2026-03-02 03:51:45 +01:00
integrator-bot deleted branch dev/issue-251-batch-a-shell-router 2026-03-02 03:51:45 +01:00